Index du Forum » » Général ABAP/MM

Auteur

EQUIVALENTS DES ARTICLES
Thierry
1  

  Posté : 24-03-2010 21:11

Comme ça, vite fait, je t' orienterais vers le champs suivant de la vue MRP 4

Discontinuation indicator MARC-KZAUS
Identifies the material as a part to be discontinued and !include!s it in the discontinued parts procedure in materials planning.
Use
If this indicator is set, the system transfers the dependent requirements in materials planning to the follow-up material if they are no longer covered by warehouse stocks. However, this requires:
• The part to be discontinued and the follow-up material to be planned using material requirements planning (MRP)
• The base unit of measure of the follow-up material to be the same as that of the part to be discontinued
Note
In subcontracting, uncovered requirements are not switched to the follow-up material after the effective-out date. This is indicated by a corresponding exception message (58) in the MRP list.

Ce champ est utilisé avec la date de mise en place MARC-AUSDT et du champ indiquant quel est le matériel de remplacement. MARC-NFMAT

J’espère répondre à ta question.



Cet article provient de Sap.technique

http://sap.technique.free.fr/viewtopic.php?topic=12&forum=7